2014 Clark's Creek Elodea Management
The in-water work window for 2014 was June 16-August 1. With a successful 2013 Diver-Assisted Suction Harvesting (DASH) clearing of the entire project area, the 2014 management was completed with the DASH method only, as outlined in the project's HPA permit.
In-water work began on June 16, 2014 and ended August 8, 2014. Daily updates from the progress and amount of elodea removed are posted below. Also posted below are the project-area maps.
2014 Project Details
In-Water Extension Granted
WDFW granted a request to extend the in-water work window by one week, as allowed by a minor modification in the HPA permit. This additional week will allow the contractor time to complete the contract work, which has been slowed by equipment failures now corrected with new pumps in the DASH boats.
Running Totals
- Total area cleared: 15,750 LF
- Total elodea removed: 29,565 bags
Updates
- 06/16 - Contractor Began In-Water Work Near the 12th Avenue SW Bridge.
Area Cleared: 200 linear feet (LF)
Bags of Elodea Removed: 150 - 06/17 - Continued Work Between 12th and 7th Avenue SW Bridges
Area Cleared: 560 LF
Bags of Elodea: 375 - 06/18 - Completed Work up to Check Point No. 1
Area Cleared: 500 LF
Bags of Elodea: 275 - 6/19 - Worked in Area No. 2
Area Cleared: 200 LF
Bags of Elodea: 225 - 6/20 - Worked in Area No. 2
Area Cleared: 250 LF
Bags of Elodea: 325 - 6/23 - Worked in Area No. 2
Area Cleared: 350 LF
Bags of Elodea: 525 - 6/24 - Worked in Area No. 2
Area Cleared: 700 LF
Bags of Elodea: 725 bags - 6/25 - Finished area No. 2
Area Cleared: 450 LF
Bags of Elodea: 675 - 6/26 - Worked in Area No. 3
Area Cleared: 550 LF
Bags of Elodea: 850 - 6/27 - Worked in Area No. 3
Area Cleared: 400 LF
Bags of Elodea: 550 - 6/30 - Worked in Area No. 3
Area Cleared: 500 LF
Bags of Elodea: 525 - 7/1 - Worked in Area No. 4
Area Cleared: 300 LF
Bags of Elodea: 450 - 7/2 - Worked in Area No. 4
Area Cleared: 500 LF
Bags of Elodea: 500 - 7/3 - Worked in Area No. 4
Area Cleared: 400 LF
Bags of Elodea: 750 - 7/7 - Worked in Area No. 4/5
Area Cleared: 600 LF
Bags of Elodea: 750 - 7/8 - Worked in Area No. 5
Area Cleared: 550 LF
Bags of Elodea: 800 - 7/9 - Worked in Area No. 5
Area Cleared: 350 LF
Bags of Elodea: 900 - 7/10 - Worked in Area No. 5
Area Cleared: 300 LF
Bags of Elodea: 1,100 - 7/11 - Worked in Area No. 5
Area Cleared: 550 LF
Bags of Elodea: 1,200 - 7/14 - Finished in Area No. 5
Area Cleared: 400 LF
Bags of Elodea: 900 - 7/15 - Worked in Area No. 6
Area Cleared: 350 LF
Bags of Elodea: 850 - 7/16 - Worked in Area No. 6
Area Cleared: 400 LF
Bags of Elodea: 1,125 - 7/17 - Worked in Area No. 6
Area Cleared: 250 LF
Bags of Elodea: 1,025 - 7/18 - Worked in Area No. 6
Area Cleared: 150 LF
Bags of Elodea: 1,250 - 7/21 - Worked in Area No. 6
Area Cleared: 250 LF
Bags of Elodea: 1,100 - 7/22 - Worked in Area No. 6
Area Cleared: 400 LF
Bags of Elodea: 1,275 - 7/23 - Worked in Area No. 6
Area Cleared: 250 LF
Bags of Elodea: 1,100 - 7/24 - Worked in Area No. 6
Area Cleared: 300 LF
Bags of Elodea: 825 - 7/25 - Worked in Area No. 6
Area Cleared: 500 LF
Bags of Elodea: 1,300 - 7/26 - Worked in Area No. 6
Area Cleared: 250 LF
Bags of Elodea: 600 - 7/28 - Worked in Area No. 6 and No. 8
Area Cleared: 600 LF
Bags of Elodea: 850 - 7/29 - Worked in Areas No. 6 and No. 8
Area Cleared: 1,100 LF
Bags of Elodea: 1,000 - 7/30 - Worked in Areas No. 6 and No. 8
Area Cleared: 1,000 LF
Bags of Elodea: 925 - 7/31 - Worked in Areas No. 6 and No. 8
Area Cleared: 600 LF
Bags of Elodea: 975 - 8/01 - Worked in Areas No. 6 and No. 8
Area Cleared: 550 LF
Bags of Elodea: 700 - 08/04 - Completed Area No. 6
Area Cleared: 600 LF
Bags of Elodea: 725 - 08/05 - Completed Area No. 8
Area Cleared: 500 LF
Bags of Elodea: 700 - 08/06 - Worked in Area No. 7
Area Cleared: 500 LF
Bags of Elodea: 1,015 - 08/07 - Completed Area No. 7
Area Cleared: 700 LF
Bags of Elodea: 975