12th Ave NW & 20th St NW Water Replacement Project

CIP Project Number: 19-015

Project Manager: Scott Tkach

Project Description:

The project includes the replacement of approximately 1,000-ft 2 inch water main pipe and associated services. The project will also replace non-conforming curb ramps, restore asphalt pavement, replace curb & gutter, enhance localized drainage at the intersection of 12th Ave NW & 18th St NW, replace defective sidewalks, replace cement concrete and asphalt driveway approaches, and mitigate  private residential landscaping impacted by construction. 

Approved Budget/Est Cost (All Phases): $512,000

Estimated Schedule: Design August 2019 to March 2020; Construction May 2020 to August 2020