Summary
This project will replace approximately 2,700 linear feet of 8-inch diameter sewer main, including side sewers and cleanouts. The project will also include improvements to stormwater facilities and the roadway, and the installation of ADA compliant ramps. The City has contracted with HCON Incorporated to perform the work.
Approved 2022 Construction Budget: $2.2 million
Estimated Construction Schedule: January 2022 to July 2022
For questions about this project, please contact Jessica Wilson via email or phone at 253-435-3645.