9th Ave SW, 5th to Meridian Street Imp.

CIP Project Number: 14-040

Project Manager: Ted Hill

Project Description:

Transforming the roadway into a pedestrian friendly by removing the curb and providing an area that can be used during when the road is closed. This project is being done in two phases, the first phase was completed in 2019, which fixed some deteriorating storm and sewer lines.

Approved Budget/Est Cost (All Phases): $3,140,000

Estimated Schedule: 

Design: January 2020 to November 2020
Construction: February 2021 to August 2021

Curbless 50 ROW