Project Description
With Council Approval, the following sidewalk gap locations were identified for design and construction:
2016 Sidewalk Link Project (Anticipated Construction Year: 2018)
- 7th Avenue SE - North sidewalk link between 13th Street SE and 14th Street SE with curb ramp upgrades at the intersection of 7th Ave SE/13th Street SE and 7th Ave SE/14th Street SE.
- 5th Avenue SE - North and south sidewalk links between 14th Street SE and 15th Street SE with curb ramp upgrades at the intersection of 5th Avenue SE/14th Street SE and 5th Avenue SE/15th Street SE.
- 7th Street SE (Moved to 2017 Sidewalks) - West sidewalk link between 27th Ave SE to Life Care Center sidewalk stub. (**Update: Moved this schedule of improvements to 2017 Sidewalk Project due to proximity of projects at 27th Ave SE**)
- Spot Location Links/Repairs - Miscellaneous Sidewalk Spot Links and Repairs throughout the Northwest and Southeast quadrants of the City.