2016 Project

2016 In-Water Work

2016 Elodea Management - DASH The regular-season elodea management window was 06/01/2016 through 08/05/2016. The contractor for the 2016 project was Aqua Dive Services.

2016 Totals

Area Cleared: 15,750 LF
Bags Filled: 31,240

The project area was completed on 07/30/2016 with touch-up work in select areas up through 08/02/2016.

Daily updates


  • 07/30/2016 - Completed project areas
    Area cleared: 250 LF
  • 07/29/2016 - Area #6
    Area cleared: 380 LF
    Bags filled: 800
  • 07/28/2016 - Area #6
    Area cleared: 300 LF
    Bags filled: 1300
  • 07/27/2016- Working in Area #6
  • Area cleared: 325 LF
  • Bags filled: 1,200
  • 07/26/2016- Working in Area #5
    Area cleared: 200 LF 
    Bags filled: 940
  • 07/25/2016- Working in Area #5
    Area cleared: 250 LF
    Bags filled: 900
  • 07/23/2016 - Working in Area #5 
    Area cleared: 200 LF
    Bags filled: 500
  • 07/22/2016- Working in Area #5
    Area cleared: 350 LF
    Bags filled: 880
  • 07/21/2016- Working in Area #5
    Area cleared: 300 LF
    Bags filled: 960
  • 07/20/2016- Working in Area #5
    Area cleared: 300 LF 
    Bags filled: 940
  • 07/19/2016- Working in Area #5 
    Area cleared: 300 LF 
    Bags filled: 1,100
  • 07/18/2016- Working in Area #5 
    Area cleared: 100 LF 
    Bags filled: 560
  • 07/16/2016- Working in Area #6 
    Area cleared: 200 LF 
    Bags filled: 400
  • 07/15/2016 - Working in Areas #5 & #6 
    Area cleared: 400 LF 
    Bags filled: 1,080
  • 07/14/2016 - Working in Areas #5 & #6 
    Area cleared: 300 LF 
    Bags filled: 880
  • 07/13/2016 - Working in Areas #5 & #6
    Area cleared: 350 LF
    Bags filled: 1,000
  • 07/12/2016 - Working in Areas #5 & #6
    Area cleared: 375 LF
    Bags filled: 1,080
  • 07/11/2016
    Area cleared: 350 LF
    Bags filled: 840
  • 07/08/2016 - Working in Areas #5 & #6
    Area cleared: 400 LF
    Bags filled: 880
  • 07/07/2016 - Working in Areas #4 & #6
    Area cleared: 325 LF
    Bags filled: 920
  • 07/06/2016 - Working in Areas #4 & #6
    Area cleared: 425 LF
    Bags filled: 740
  • 07/05/2016 - Working in Areas #4 & #8
    Area cleared: 700 LF
    Bags filled: 780
  • 07/01/2016 - Working in Areas #4 & #8
    Area cleared: 500 LF
    Bags filled: 860
  • 06/30/2016 - Working in Areas #4 & #8
    Area cleared: 650 LF
    Bags filled: 860
  • 06/29/2016 - Working in Areas #4 & #8
    Area cleared: 450 LF
    Bags filled: 840
  • 06/28/2016 - Working in Areas #4 & #8
    Area cleared: 700 LF
    Bags filled: 680
  • 06/27/2016 - Working in Areas #3 & #8
    Area cleared: 470 LF
    Bags filled: 760
  • 06/24/2016 - Working in Areas #3 & #7
    Area cleared: 375 LF
    Bags filled: 560
  • 06/23/2016 - Working in Areas #3 & #7
    Area cleared: 425 LF
    Bags filled: 700
  • 06/22/2016 - Working in Areas #3 & #7
    Area cleared: 625 LF
    Bags filled: 880
  • 06/21/2016 - Working in Areas #3 & #7
    Area cleared: 425 LF
    Bags filled: 720
  • 06/20/2016 - Completed Area #2, working in Area #7
    Area cleared: 400 LF
    Bags filled: 680
  • 06/17 - Working in Areas #2 & #7
    Area cleared: 450 LF
    Bags filled: 830
  • 06/16 - Working in Areas #2 & #7
    Area cleared: 550 LF
    Bags filled: 760
  • 06/15 - Working in Area #2
    Area cleared: 575 LF
    Bags filled: 700
  • 06/14 - Working in Area #2
    Area cleared: 250 LF
    Bags filled: 240
  • 06/13 - Continued in Area #2 & #7
    Area cleared: 250 LF
    Bags filled: 750
  • 06/10 - Continued in Area #2
    Area cleared: 300 LF
    Bags filled: 640
  • 06/09 - Re-working Area #1, began Area #2
    Area cleared: 200 LF
    Bags filled: 280
  • 06/08 - Completed work in Area #1
    Area cleared: 330 LF
    Bags filled: 180
  • 06/07 - Continued work in Area #1
    Area cleared: 400 LF
    Bags filled:    240
  • 06/06 - Contractor began in-water work south of the 12th Ave SW bridge.
    Area cleared: 345 LF
    Bags filled:    400
  • 06/03 - Contractor mobilized and prepped for in-water work
    Area cleared: 0 linear feet (LF)