2016 Project
2016 In-Water Work
2016 Elodea Management - DASH The regular-season elodea management window was 06/01/2016 through 08/05/2016. The contractor for the 2016 project was Aqua Dive Services.2016 Totals
Area Cleared: 15,750 LFBags Filled: 31,240
The project area was completed on 07/30/2016 with touch-up work in select areas up through 08/02/2016.
Daily updates
- 07/30/2016 - Completed project areas
Area cleared: 250 LF - 07/29/2016 - Area #6
Area cleared: 380 LF
Bags filled: 800 - 07/28/2016 - Area #6
Area cleared: 300 LF
Bags filled: 1300 - 07/27/2016- Working in Area #6
- Area cleared: 325 LF
- Bags filled: 1,200
- 07/26/2016- Working in Area #5
Area cleared: 200 LF
Bags filled: 940 - 07/25/2016- Working in Area #5
Area cleared: 250 LF
Bags filled: 900 - 07/23/2016 - Working in Area #5
Area cleared: 200 LF
Bags filled: 500 - 07/22/2016- Working in Area #5
Area cleared: 350 LF
Bags filled: 880 - 07/21/2016- Working in Area #5
Area cleared: 300 LF
Bags filled: 960 - 07/20/2016- Working in Area #5
Area cleared: 300 LF
Bags filled: 940 - 07/19/2016- Working in Area #5
Area cleared: 300 LF
Bags filled: 1,100 - 07/18/2016- Working in Area #5
Area cleared: 100 LF
Bags filled: 560 - 07/16/2016- Working in Area #6
Area cleared: 200 LF
Bags filled: 400 - 07/15/2016 - Working in Areas #5 & #6
Area cleared: 400 LF
Bags filled: 1,080 - 07/14/2016 - Working in Areas #5 & #6
Area cleared: 300 LF
Bags filled: 880 - 07/13/2016 - Working in Areas #5 & #6
Area cleared: 350 LF
Bags filled: 1,000 - 07/12/2016 - Working in Areas #5 & #6
Area cleared: 375 LF
Bags filled: 1,080 - 07/11/2016
Area cleared: 350 LF
Bags filled: 840 - 07/08/2016 - Working in Areas #5 & #6
Area cleared: 400 LF
Bags filled: 880 - 07/07/2016 - Working in Areas #4 & #6
Area cleared: 325 LF
Bags filled: 920 - 07/06/2016 - Working in Areas #4 & #6
Area cleared: 425 LF
Bags filled: 740 - 07/05/2016 - Working in Areas #4 & #8
Area cleared: 700 LF
Bags filled: 780 - 07/01/2016 - Working in Areas #4 & #8
Area cleared: 500 LF
Bags filled: 860 - 06/30/2016 - Working in Areas #4 & #8
Area cleared: 650 LF
Bags filled: 860 - 06/29/2016 - Working in Areas #4 & #8
Area cleared: 450 LF
Bags filled: 840 - 06/28/2016 - Working in Areas #4 & #8
Area cleared: 700 LF
Bags filled: 680 - 06/27/2016 - Working in Areas #3 & #8
Area cleared: 470 LF
Bags filled: 760 - 06/24/2016 - Working in Areas #3 & #7
Area cleared: 375 LF
Bags filled: 560 - 06/23/2016 - Working in Areas #3 & #7
Area cleared: 425 LF
Bags filled: 700 - 06/22/2016 - Working in Areas #3 & #7
Area cleared: 625 LF
Bags filled: 880 - 06/21/2016 - Working in Areas #3 & #7
Area cleared: 425 LF
Bags filled: 720 - 06/20/2016 - Completed Area #2, working in Area #7
Area cleared: 400 LF
Bags filled: 680 - 06/17 - Working in Areas #2 & #7
Area cleared: 450 LF
Bags filled: 830 - 06/16 - Working in Areas #2 & #7
Area cleared: 550 LF
Bags filled: 760 - 06/15 - Working in Area #2
Area cleared: 575 LF
Bags filled: 700 - 06/14 - Working in Area #2
Area cleared: 250 LF
Bags filled: 240 - 06/13 - Continued in Area #2 & #7
Area cleared: 250 LF
Bags filled: 750 - 06/10 - Continued in Area #2
Area cleared: 300 LF
Bags filled: 640 - 06/09 - Re-working Area #1, began Area #2
Area cleared: 200 LF
Bags filled: 280 - 06/08 - Completed work in Area #1
Area cleared: 330 LF
Bags filled: 180 - 06/07 - Continued work in Area #1
Area cleared: 400 LF
Bags filled: 240 - 06/06 - Contractor began in-water work south of the 12th Ave SW bridge.
Area cleared: 345 LF
Bags filled: 400 - 06/03 - Contractor mobilized and prepped for in-water work
Area cleared: 0 linear feet (LF)